Road Work

ODOT Updates

ODOT Construction Update 4/17/25

Beginning Monday, April 21, 2025, nightly closures will occur at the SR2/269 (Lakeside/Marblehead) exit. Guardrail replacement and paving will be done. It is expected to last 30 days or less. The closures will be from 7 p.m. until 6 a.m. The project will begin with the off ramps, then will switch to the on ramps.

ODOT Construction Update 4/7/25

The current project on the Edison Bridge is being done to replace all the box beam railing near the District 2 (Ottawa County) side. Some barrier wall will also be replaced as well as all the guardrail on the SR 269 ramp and SR 163 ramps. The guardrail work should be completed when paving is finished on SR 2 and the 269 ramps. The completion date is May 31. On April 7 and 8 the on ramps from SR 163 to SR 2 will be closed. On April 9 and 10 the off ramps from SR 2 to SR 163 will be closed.